North Carolina Solar Procurement Faces 2026 Setback
The year 2026 has been officially designated as a year of lost solar opportunity in North Carolina. This designation follows a series of regulatory decisions that have effectively halted new large-scale solar contract bidding for Duke Energy. Critics have labeled the actions by the state’s top utility regulator as arbitrary and capricious, raising concerns about the legality and impact of these decisions on the state’s clean energy transition.
Table of Contents
Initially, the abrupt cancellation of bidding for 2026 solar contracts in the spring led to numerous legal challenges. As these proceedings extended through the summer and fall, the clean energy sector grew increasingly concerned about the dwindling timeline. The lack of timely decisions meant that Duke Energy would be unable to solicit proposals for new solar projects within the year.
Regulatory Rulings Cement Solar Procurement Loss
The loss of 2026 solar procurement is now official. In a decision approving Duke Energy’s long-term carbon reduction plan, the North Carolina Utilities Commission ruled that certain solar megawatts planned for 2026 would be deferred to future years. This decision came after the commission rejected appeals from clean energy trade groups and environmental nonprofits seeking reconsideration of the earlier order.
Consequently, Duke Energy will now contract for an additional 2.3 gigawatts of solar capacity to be operational by 2034. This adjustment, stemming from the 2021 state law, brings the total planned solar addition to approximately 6.4 GW. However, this revised figure reflects a significant reduction, including over a gigawatt of solar capacity foregone in 2026 alone.
“We just completely skipped a year of solar procurement in the state,” stated Nick Jimenez, senior attorney with the Southern Environmental Law Center. This missed opportunity represents a significant blow to bringing low-cost, clean generation online in North Carolina, impacting both energy consumers and environmental goals.
Economic Headwinds and Policy Shifts Impact Solar Investment
Advocates point to several factors contributing to this setback in North Carolina solar procurement. Punitive tariffs and expiring tax credits, previously enacted under the Trump administration, have increased the cost of renewable energy resources. The commission’s orders acknowledged that these policies make solar power more expensive for consumers.
Furthermore, a legislative change last year repealed a requirement for Duke Energy to reduce its carbon pollution by 70% by 2030. This repeal, driven by a Republican-led state legislature, has led to a perceived reduced near-term need for solar energy, contributing to the commission’s decision to defer procurement.
Carson Harkrader, chair of the Carolinas Clean Energy Business Association, emphasized the economic implications. “We can no longer expect that the price of solar is going to go down every year,” she noted. Pushing out solar procurements means losing the opportunity to lock in lower prices, ultimately leading to higher costs for ratepayers in the long run.
Industry Pushes for Accelerated Future Procurement
Despite the challenges, the solar industry remains committed to meeting North Carolina’s energy needs. Industry leaders are preparing to compensate for the lost 2026 procurement by aiming for higher annual targets in subsequent years. This strategy acknowledges that while playing catch-up is possible, it will likely come at a greater expense due to ongoing inflation and tariff pressures.
“Our members remain committed to this market, to driving down costs for ratepayers, and to bringing projects online quickly to meet our state’s energy needs,” Harkrader added. The industry has demonstrated the capacity to install significant volumes of utility-scale solar annually in the past, suggesting that accelerated future procurement is technically feasible.
Duke Energy, while acknowledging the need to adjust its plans, stated that procuring 2.3 GW of solar by the end of 2028 remains achievable. The company is required to provide the commission with a revised plan detailing how it intends to meet these projections within ten days. This plan will be crucial in determining the path forward for solar development in the state.
Ensuring Business Certainty for Future Growth
Moving forward, consistent regulatory signals and clear utility procurement plans are deemed vital by industry stakeholders. Business certainty and predictable annual procurements enable solar companies to plan investments effectively, fostering competition and driving down costs for consumers. This predictability is essential for the continued growth and integration of solar power into North Carolina’s energy mix.
The situation underscores the complex interplay between regulatory policy, economic factors, and technological advancement in the clean energy sector. While the loss of 2026 North Carolina solar procurement presents a significant hurdle, the industry’s resilience and commitment offer a path toward meeting future energy demands, albeit with potentially higher costs.
Elizabeth Ouzts is a contributing reporter at Canary Media who covers North Carolina and Virginia.